Which form for which jobA shower upgrade. EIC or Minor Works?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The question at the end: A shower upgrade. EIC or Minor Works? The answer is in the notes below.
The notes
Exactly as they are on the site.
Worked through as a series of scenarios:
| The work | Form |
|---|---|
| A new circuit added to the installation | EIC |
| Adding a socket to an existing circuit | Minor Works (an EIC would also be acceptable) |
| Consumer unit change | EIC |
| Upgrading a 7 kW shower to 9.5 kW, needing a bigger cable | EIC — the circuit's cable is replaced, and the testing changes |
| Replacing a circuit's cable with a different type | EIC — the circuit is rewired |
| Like-for-like replacement — 2.5 mm² twin and earth for the same | Minor Works |
| Like-for-like RCD replacement | Minor Works |
The question to ask is whether a new circuit is involved — or a new consumer unit, or a circuit's cable replaced. If not, an addition or alteration to an existing circuit, or a straight swap of the same thing for the same thing, is Minor Works.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing