The whole installation — a worked board
A domestic board whose protective devices total 130 A:
| Circuit | Device |
|---|---|
| Ring final | 32 A |
| Kitchen ring | 32 A |
| Cooker | 32 A |
| Immersion heater | 16 A |
| Lighting, upstairs | 6 A |
| Lighting, downstairs | 6 A |
| Smoke alarms | 6 A |
| Total | 130 A |
Which is why the supply is sized on maximum demand, not on the sum of the devices.
Are these standard circuits?
The question that decides which entry of Table A2 you use. On-Site Guide · Appendix H sets out the standard arrangements of final circuits. An ordinary domestic board is all standard circuits.
Table A2, item 9 — standard circuits
In On-Site Guide · Table A2, item 9 (p.152) is the “Standard arrangement of final circuits in accordance with Appendix H”. For a household installation it says:
| Step | Working | Result |
|---|---|---|
| Total of all protective devices | 130 A | |
| Set aside the largest circuit at 100% | one of the 32 A circuits | 32 A |
| What remains | 130 − 32 | 98 A |
| 40% of the remainder | 98 × 0.4 | 39.2 A |
| Maximum demand | 32 + 39.2 | 71.2 A |
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing