The schedule of test results, set up before you start
A blank results sheet looks like a hundred empty boxes. Most of them can be dealt with before you test anything:
- Draw a line through every spare.
- N/A the ring columns (r1, rn, r2) for every circuit that isn’t a ring.
- Decide whether you’re proving CPCs by Method 1 or Method 2, and N/A the column you’re not using.
- Write in your insulation resistance test voltage, 500 V for a 230 V installation.
- N/A the AFDD test-button column for circuits with no AFDD.
- Fill in the instruments: make, model and serial number against each test function. One multifunction tester can cover several, and you N/A any function you’re not using.
At the top of the sheet, for the board itself, you’ll later record Zdb (on the main board, the box takes your Ze), the prospective fault current at the board, polarity confirmed, phase sequence on a three-phase board, and the SPD’s operational status.
Where each result goes, in test order
Following the sequence of tests, this is where each result is written, and which boxes on the certificate you go back and tick.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing