The intake: from service head to circuitsWhat belongs to the DNO, and what belongs to you?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
- Adding a consumer unit (e.g. for a garage or EV charger): a Henley block (connector block) splits the tails after the meter. It's usually fitted by the DNO or supplier.
- Older consumer units used rewireable fuses (BS 3036), which have fuse wire in a carrier. You'll still find them.
Mains position: separation from gas
- Keep at least 25 mm between the supply or distribution cable and domestic gas pipework up to 35 mm. For pipework over 35 mm, keep 50 mm.
- You can reduce this if the gas pipe is PVC-wrapped or there's an insulating barrier.
- Keep at least 150 mm between the gas meter and the electrical intake or consumer unit.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing