Free notes
The eleven steps of cable selection: design current and InA 9 kW shower. What's the design current?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
The eleven steps of cable selection
From a kilowatt rating to a verified cable, CPC and protective device. Most people stop around step 7, at volt drop — which is halfway.
| Step | Find | Where |
|---|---|---|
| 1 | Ib — design current | P ÷ V |
| 2 | In — device rating | Table 41.3 / B6 / A6 |
| 3 | Reference method | BS 7671 Appendix 4, Table 4A2 |
| 4 | Correction factors | Appendix 4 — Ca, Cg, Ci, Cf |
| 5 | It needed — required capacity | In ÷ the factors |
| 6 | It — tabulated capacity → cable size | Table 4D5 for twin and earth |
| 7 | Volt drop | Same table — mV/A/m |
| 8 | Expected R1+R2 | GN3 Appendix B / OSG Appendix I |
| 9 | Zs, checked against the maximum | Ze + (R1+R2) |
| 10 | Ipf | U0 × Cmin ÷ Zs |
| 11 | CPC size — adiabatic | BS 7671 Chapter 54 |
Step 1 — design current
Step 2 — In, and whether diversity applies
Check Table A2 before assuming diversity. For an instantaneous water heater or shower, the entry is either 100% of the largest appliance or no diversity allowed — so either way, the full 39.13 A stands. Nothing to reduce.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing