The EIC page 2: supply characteristics

Page two is where the installation gets described in numbers. Most of it is ticks.

FieldWhat you put
Earthing arrangementTN-S or TN-C-S on most installations — and tick PME if it's TN-C-S. The form lists other arrangements as well, but most installations you meet will be one of these two
AC or DCAC
Number of wiresSingle-phase two-wire, three-phase four-wire — "wires" means lines plus neutral
Nominal voltage230 V single phase · 400/230 V three phase (put the 400 in first)
Frequency50 Hz
Maximum demandThe demand after diversity, in amps or kVA. The form says “kVA / A”, so delete the one you’re not using. It is not the main fuse or main switch rating — those have their own boxes. Guidance Note 3, 2.3
✋Two boxes on this page are LIVE tests. Ze (external earth fault loop impedance) and PFC (prospective fault current) cannot be filled in during dead testing. You either measure them live, or obtain them by enquiry of the DNO. In practice everyone measures — nobody's ringing the DNO and waiting for a reply when they'll be on site doing live tests anyway.
Earth electrode. If there isn't one — and on TN-S or TN-C-S there won't be — that block gets N/A right through.

GN3 · Section 5 · the EIC · example EIC, Figures 5.1–5.3, pp.147–149 ★ BS 7671 · Appendix 6 · model forms

Earthing, bonding and the main switch

Sizing, straight off tables you already know

From the incoming tails

25 mm² tails
→ earthing conductor 16 mm²
→ main protective bonding 10 mm²  (read the table: Electrician's Guide Table 3.3.2b, PME)

The tables: Electrician's Guide Tables 3.3.2a (TN-S) and 3.3.2b (PME), p.59, or BS 7671 Tables 54.7 and 54.8. 16, 25 and 35 mm² tails all give you a 16 mm² earthing conductor. Main bonding you read off the table too — don't work it out by halving: on PME it's 10 mm² for supplies up to 35 mm².

Connection verified, or continuity verified?

?Two different tick boxes, and they mean different things. You can see that a conductor is connected. You cannot see that it has continuity — that has to be tested.
Continuity of the main protective bonding is your first dead test. Before anything else on the circuits.

You also tick what's actually bonded: water, gas, oil, structural steelwork, lightning protection. In a domestic property it's usually just water and gas. The material is normally copper.

The main switch, and the sticker that catches everyone

You record the main switch's location, its BS EN number, the number of poles, its rating and its voltage. Poles: two for single phase (line and neutral), four for three phase (three lines and neutral).

✋The BS EN number trap, again. Boards come with a sticker sheet, and the number printed under "main switch" on the consumer unit cover is often the number for the consumer unit itself. Your main switch is BS EN 60947-3, and that number is printed on the side or bottom of the switch body. Read it off the device.

EG · Tables 3.3.2a and 3.3.2b · p.59 · earthing and bonding sizes ★ BS 7671 · Tables 54.7 and 54.8 ★ BS EN 60947-3 · the main switch ★

Test yourself on it

The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.

Get access

Get new notes and exam tips from Sparky

About one email a fortnight. Unsubscribe any time. Privacy notice

That was one section. There are 583.

Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.

  • 583sections of written notes
  • 35video lessons
  • 1,463practice questions
  • 146diagrams, redrawn
  • 18th Edition
  • Building Regs
  • PAT
  • Fundamental Inspection & Testing
  • Initial Verification
  • Periodic Inspection & Testing
Get access — £100 12 months. One payment. See what’s inside