Testing the main protective bondingWhat has to be true before a bond comes off?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
This is method 2’s real job. And it starts with one rule that is not negotiable.
- Installation isolated. Disconnect one main protective bonding conductor from the MET. Only one at a time.
- Clip the long lead to the disconnected bonding conductor, on clean copper.
- Probe the bonding clamp at the pipe — the screw, or a clean part of the clamp.
- Then probe the pipe itself, on clean metal. That proves the clamp is actually connected to the pipe, not just sitting on it.
- Reconnect it. Every time, before the next one comes off.
Guidance Note 3 · 2.6.5 · parallel earth paths · bonding conductors · the wander lead figure · p.62
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing