Supplementary bonding links exposed and extraneous conductive parts locally, e.g. the metal pipes under a bath to a metal shower, so they stay at the same potential. You'll often see it as a loop of green/yellow between copper pipes, such as at a boiler. Somewhere along those pipes, a main bonding conductor goes back to the MET.
- All final circuits in the location meet automatic disconnection of supply (ADS): a CB within the Table 41.1 time (0.4 s TN, 0.2 s TT), a 30 mA RCD within 300 ms.
- All final circuits in the location have additional protection by a 30 mA RCD.
- All extraneous conductive parts are effectively connected to the main protective bonding (back to the MET).
BS 7671 · Section 701: locations containing a bath or shower — starts p.257 BS 7671 · Reg 701.415.2 supplementary bonding, and when it may be omitted · p.258
Supplementary bonding conductor sizes
This depends on what you're linking and whether the conductor is mechanically protected, e.g. in conduit. A single-core green/yellow conductor has only one layer of insulation. The grey sheath on twin and earth is mechanical protection, and an RCD is additional protection, not mechanical.
Worked example
CPC of the circuit feeding the exposed part = 10 mm² Link: electric shower (exposed part) → pipes under the bath (extraneous part) Not mechanically protected → 6 mm² (still 6 mm² if protected) Exposed part → exposed part, both mechanically protected with 10 mm² → 10 mm²
Electrician's Guide to the Building Regs · 3.3.3 Supplementary bonding conductors · Table 3.3.3 sizes · p.62
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing