Proved dead is not finished: the other six stepsWhy a volt stick as well as your AVI?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
Everything up to here is one step of the eight. The installation being dead is what lets you do the rest safely; it is not the end of the check.
| # | What you do | What you expect |
|---|---|---|
| 3 | Clamp the earthing conductor and main bonding again, now it is off | Current dropped to zero, or to an extremely small level |
| 4 | Volt stick at the MET, along the earthing conductor, along each main bonding conductor, and at the extraneous-conductive-parts | No voltage indicated |
| 5 | Disconnect the main protective bonding conductors | Nothing unusual |
| 6 | Volt stick again, same places | No voltage indicated |
| 7 | Reconnect the main protective bonding conductors | Nothing unusual |
| 8 | On a TN system, check the external earth fault loop impedance during your inspection and testing | A sensible Ze — see below |
Step 8 — and a number you have already met
As a rule of thumb, Ze up to about 0.35 Ω on TN-C-S and 0.80 Ω on TN-S. A reading that is high is the signal.
Guidance Note 3 · Appendix D · the eight steps
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing