Our example installation

To cover every case, we'll use one installation with five circuits. It's on a TN-S earthing arrangement, which is common in the UK. It doesn't matter whether it's domestic, commercial or industrial. The rules are the same.

  • The supply enters the building and feeds DB1.
  • DB1 has two final circuits (red and green) and one distribution circuit (yellow) that feeds DB2.
  • DB2 has two final circuits (blue and purple).
TN-S supply DB1 32 A socket circuit 1 40 A fixed load 2 3 distribution circuit to DB2 DB2 32 A fixed load 4 80 A socket circuit 5 Final circuits: 1, 2, 4, 5 · Distribution circuit: 3
Drawn for these notes. Five circuits, one of each type you'll meet: 1 sockets 32 A, 2 fixed 40 A, 3 distribution, 4 fixed 32 A, 5 sockets 80 A.

Final circuit or distribution circuit?

Final circuit
A circuit that is finally being used: it supplies the lights, the heaters, the cooker, the shower or the socket-outlets directly.
Distribution circuit
A circuit that feeds another distribution board (like the yellow submain from DB1 to DB2). It doesn't supply the equipment itself.

BS 7671 · Part 2 Definitions · "Circuit, final" and "Circuit, distribution" Worth a read. Check your copy for the page

Working through the five circuits

For each circuit, ask: Is it a final circuit? Does it supply sockets or fixed equipment? What's its rating?

CircuitWhat it isWhich ruleMax time (TN, 230 V)
1 · redFinal circuit, sockets, 32 A (a typical ring or radial)Table 41.1 (sockets ≤ 63 A)0.4 s
2 · greenFinal circuit, fixed equipment, 40 A (e.g. a shower)Reg 411.3.2.3 (fixed > 32 A)5 s
3 · yellowDistribution circuit, DB1 to DB2Reg 411.3.2.3 (never Table 41.1)5 s
4 · blueFinal circuit, fixed equipment, 32 A (e.g. a cooker)Table 41.1 (fixed ≤ 32 A)0.4 s
5 · purpleFinal circuit, sockets, 80 AReg 411.3.2.3 (sockets > 63 A)5 s

If the installation were TT instead, circuits 2, 3 and 5 would use Reg 411.3.2.4 (up to 1 s), and circuits 1 and 4 would use the TT row of Table 41.1 (0.2 s).

"Fixed equipment" means

Anything that's fixed current-using equipment rather than something that plugs in. In practice it's any circuit that isn't a socket circuit: a shower, a cooker, a heater.

The DB2 trap

Common mistake
Some people think that because DB2 is fed by a distribution circuit, the circuits from DB2 can't be final circuits. Wrong. Circuits 4 and 5 are still final circuits. Look at each circuit on its own, not at what feeds its board.

Sockets above 63 A?

You'll almost never see this in a house, but it happens in commercial and industrial work. A "socket-outlet" isn't only a 13 A 3-pin socket on a wall. It's anything classed as a socket, such as an industrial socket for a large machine that plugs in and draws a high current.

Test yourself on it

The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.

Get access

Get new notes and exam tips from Sparky

About one email a fortnight. Unsubscribe any time. Privacy notice

That was one section. There are 583.

Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.

  • 583sections of written notes
  • 35video lessons
  • 1,463practice questions
  • 146diagrams, redrawn
  • 18th Edition
  • Building Regs
  • PAT
  • Fundamental Inspection & Testing
  • Initial Verification
  • Periodic Inspection & Testing
Get access — £100 12 months. One payment. See what’s inside