Minor work doesn't involve a new circuit. It's an alteration or addition to an existing installation.

NOT notifiable (minor work)
  • Replacing accessories: sockets, switches, ceiling roses
  • Replacing a single circuit's cable, same size and same route
  • Refixing or replacing enclosures of existing components
  • Adding mechanical protection to existing fixed wiring (conduit, trunking)

Also not notifiable, as long as it's NOT in a special location:

  • Adding lighting points to an existing circuit
  • Adding sockets or fused spurs to an existing ring or radial
  • Installing or upgrading main or supplementary bonding
  • An outside light or socket fed from an existing circuit, e.g. an IP65/66 socket through the wall from a kitchen socket
Notifiable
  • A new circuit, e.g. a new cooker or shower circuit
  • Replacing a consumer unit
  • Any addition or alteration to circuits in a special location

EV chargers and solar PV count as notifiable, and each has its own guidance.

Electrician's Guide to the Building Regs · Notifiable work table · p.29 Highlight this table: it matters

Electrician's Guide to the Building Regs · 1.6 Non-notifiable work (list) · p.30

Don't confuse Part P with BS 7671. Non-notifiable work must still comply with BS 7671 and still be inspected, tested and certified. For minor work that means a Minor Electrical Installation Works Certificate (MEIWC).

Plugging in an extension lead isn't installation work, because it isn't fixed wiring. Replacing twin and earth with singles in conduit is a new circuit, so it's notifiable.

Test yourself on it

The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.

Get access

Get new notes and exam tips from Sparky

About one email a fortnight. Unsubscribe any time. Privacy notice

That was one section. There are 583.

Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.

  • 583sections of written notes
  • 35video lessons
  • 1,463practice questions
  • 146diagrams, redrawn
  • 18th Edition
  • Building Regs
  • PAT
  • Fundamental Inspection & Testing
  • Initial Verification
  • Periodic Inspection & Testing
Get access — £100 12 months. One payment. See what’s inside