Metal conduit as the cpc

In a lot of metal installations the actual cpc is the metal conduit — and this is something you may well meet in your practical assessment.

How the earth path runs

Metal conduit, earthed at each end of the run
  -> into the metal back box (also earthed)
  -> fly lead from the back box to the front plate
  -> and the cpc of the twin and earth cable back to the MET
You have three legitimate options. Use the metal conduit as the cpc; run a separate cpc inside it; or do both. Both is not required — it is belt and braces — but some people do it.
Either way the conduit gets earthed. It is an exposed conductive part, so it is earthed back to the MET: a fault to it then makes the protective device operate. Terminated with a brass bush or earthing ring and a lock nut.
Types, and a word on names. Black enamel, stainless steel and galvanised steel conduit, alongside PVC. "EMT" is an American term — here it is just metal conduit. And earthing buried conduit matters more because of where it sits: back to your installation reference methods.

SWA, and circuits with no neutral

The armour of steel wire armoured cable can be used as the cpc.

A three-phase circuit may have no neutral at all. With balanced loads you do not need one — the primary side of a transformer carries only the three line conductors, and so can a balanced motor. The neutral comes from the star point on the secondary side.

Using three-core SWA for a single-phase circuit

You sleeve the cores to identify them.

Which colour you use for which does not matter —
what matters is that both ends match.
The conductor that is a neutral at the accessory must land in
the neutral bar at the consumer unit.
The same discipline as two-way switching. The two ends have to marry up. One convention is blue on the grey and green-and-yellow on the black — but it is only a convention. Others may do it differently, and that is fine — as long as both ends match.

Test yourself on it

The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.

Get access

Get new notes and exam tips from Sparky

About one email a fortnight. Unsubscribe any time. Privacy notice

That was one section. There are 583.

Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.

  • 583sections of written notes
  • 35video lessons
  • 1,463practice questions
  • 146diagrams, redrawn
  • 18th Edition
  • Building Regs
  • PAT
  • Fundamental Inspection & Testing
  • Initial Verification
  • Periodic Inspection & Testing
Get access — £100 12 months. One payment. See what’s inside