The notes
Exactly as they are on the site.
To stop this happening, we bond the extraneous conductive parts to the MET with main protective bonding conductors (MPBC).
- Connect them with an earth clamp to BS 951. It's a strap that wraps around the pipe and screws tight, with a separate terminal for the conductor.
- Don't strip a bonding conductor and wrap it around the pipe held on with tape. It does get done, but it's not the right way.
- Every time a metal pipe comes up out of the ground inside the premises, it's an extraneous conductive part and needs its own bond. In our drawing the water pipe splits, goes back under the ground and comes up elsewhere, so the installation needs three MPBCs: gas, water, and the re-emerging branch.
Main protective bonding conductors should be terminated within 600 mm on the consumer's side of valves and meters, or where the service enters the building, and before any branch pipework.
- Gas meter outside in a box on the wall (common in houses)? Bond where the gas pipe comes into the building, within 600 mm.
- Never on the supplier's side. That pipework belongs to the supplier, who could alter it and disconnect your bond.
- Before any branch. Every cut, fitting and soldered joint adds resistance, and the whole point is the lowest possible resistance between the pipe and the MET.
Bonding makes the extraneous conductive parts the same potential as the MET. The MET is connected to the exposed conductive parts and to the star point, so everything is at the same potential. Before bonding, the potential difference between the faulty exposed part and the pipe was 230 V. After bonding, it's (near enough) gone. Put the person back in the drawing and they feel nothing.
It minimises the risk of electric shock by reducing the potential difference between exposed and extraneous conductive parts. It does this by raising them all to the same potential using heavy copper bonding conductors.
BS 951 · earth clamp standard BS 7671 · Reg 544.1.2 location of main bonding connections (600 mm, consumer's side, before branches) · check your copy for the page Reg number added for reference
Electrician's Guide to the Building Regs · 3.3.2 list of services to bond Electrician's Guide to the Building Regs · plastic pipes, bonding within 600 mm · p.59 On-Site Guide · Section 4 earthing and main bonding figure
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing