SPARKYSTUDY NOTES

Free notes

How to notify: the three routesThree ways to get notifiable work signed off. Know them?

Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.

From Sparky’s full video lesson. Members get the whole lesson on every notes page.

The notes

Exactly as they are on the site.

Download these notesPDF · free to keep

Notifiable work must be pre-notified to Local Authority Building Control (your local council) unless it's an emergency, or unless the person doing the work is in a competent person scheme. "Person" is a legal term meaning the firm or sole trader doing the work.

1

Join a Competent Person Scheme (CPS)

e.g. NICEIC or NAPIT. No need to pre-notify, so you can start straight away.

  • The work must be notified, through your scheme, within 30 days of being completed
  • The scheme sends a Building Regulations Compliance Certificate to the householder and Building Control
  • You still issue your BS 7671 certificates to the client

Rough cost: NICEIC £750–850/year · NAPIT £500–600/year plus a fee per notification. You get a 24/7 technical helpline, discounted books and less admin. If you work for a registered company, you'll usually be covered by their scheme.

2

Use a registered third-party certifier

Pay someone who is registered to inspect, certify and sign off your work, and notify on your behalf.

  • Tell the certifier within 5 days of finishing the work
  • The work is then notified within 30 days
3

Notify Building Control yourself

Before starting, submit a building notice or full plans. Allow up to about 30 days. Building Control then becomes responsible for checking the work.

  • If you're qualified to complete BS 7671 certificates, give Building Control a copy. They decide what further inspection is needed.
  • They may issue a completion certificate or inspect it themselves
  • Build a good relationship with your local council. Once they trust your work, they're less likely to inspect every job.

Electrician's Guide to the Building Regs · 1.4.1 Prior notification · 1.4.2 Competent person · 1.4.3 Registered third-party certifier · 1.4.4 Conditions of authorisation · pp.24–27 Electrician's Guide to the Building Regs · 1.4.5 Certification by a building control body · 1.4.6 Unregistered persons · p.27 Highlight 1.4.1 to 1.4.6. Exam questions ask about notification methods.

Worth weighing (not advice)
If 90% of your work is non-notifiable, a scheme costing around £500–850 a year may not be worth it for the other 10%. Notify Building Control yourself and put the cost in your quote. If most of your work is notifiable, join a scheme. Never turn work down just because it's notifiable. In an emergency, make it safe. You can't leave something dangerous.

Test yourself on it

The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.

Get access

Get new notes and exam tips from Sparky

About one email a fortnight. Unsubscribe any time. Privacy notice

That was one section. There are 583.

Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.

  • 583sections of written notes
  • 35video lessons
  • 1,463practice questions
  • 146diagrams, redrawn
  • 18th Edition
  • Building Regs
  • PAT
  • Fundamental Inspection & Testing
  • Initial Verification
  • Periodic Inspection & Testing
Get access — £100 12 months. One payment. See what’s inside