Guidance Note 3 · 2.6.13 · pp.78–83 (E1 p.78, Figure 2.26 p.79, E2 p.80, E3 p.83). Three methods, and the thing to remember is that they are not all dead tests.
| Method | What you do | Dead or live | Accuracy |
|---|---|---|---|
| E1 | Test directly on the electrode. A dead test: the earthing conductor is disconnected. | Dead | Most accurate |
| E2 | Clamp around the earthing conductor — single-coil or two-coil. The conductor stays connected to the MET and the other rods stay in, so the supply can stay on. Then apply the formula. | Live | More accurate if there are a number of earth electrodes |
| E3 | An earth fault loop impedance test — effectively a Ze test, taken at the incoming supply. Main switch off and the earthing conductor disconnected, usually at the MET — but your leads are on the live supply side. | Live | May not be as accurate as a dedicated earth electrode tester |
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing