Disconnection times outside Table 41.1: 5 s and 1 sWhy are 5 seconds allowed?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
After Table 41.1 come two regulations, one for each earthing system. They cover distribution circuits and any circuit not covered by 411.3.2.2:
A disconnection time not exceeding 5 s is permitted.
A disconnection time not exceeding 1 s is permitted.
BS 7671 · Reg 411.3.2.3 TN: up to 5 s · Reg 411.3.2.4 TT: up to 1 s · p.72
It doesn't have to. That's the wrong way to look at it. 5 s is the maximum allowed, not how long it will take. As a designer, you need to know the required time so that you can design the circuit to disconnect within it. For the yellow distribution circuit, you know you're allowed up to 5 s, so that's the limit you work to in your calculations.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing