Cable calculation, step 14: the adiabatic check on the CPCWill the CPC survive until the device trips?
Free from the notes: Sparky’s video on it, the section word for word as members see it, and a PDF to keep.
The notes
Exactly as they are on the site.
S = minimum CPC size (mm²) · I = fault current (A) · t = disconnection time (s) · k = a factor for the conductor and insulation material and temperatures
k comes from Chapter 54, Tables 54.2 to 54.6. Ours is Table 54.3: a protective conductor incorporated in a cable or bunched with cables, initial temperature 70 °C or more. For 70 °C thermoplastic, copper: k = 115. The starred 103 is for conductors over 300 mm². Ours is 6 mm², so 115.
Working
S = √(550.4² × 0.1) ÷ 115 = √30 294 ÷ 115 = 174.1 ÷ 115 = 1.51 mm² The CPC of the designed circuit is 6 mm². Chapter 54 minimum allowable is 1.51 mm². 6 mm² ≥ 1.51 mm² ✓
BS 7671 · Chapter 54 · Tables 54.2–54.6 · values of k BS 7671 · Table 54.3 · k for a CPC in a cable or bunched (70 °C thermoplastic copper = 115)
That's the design finished. It works in normal use, and in a fault the protective device will operate before the CPC is damaged.
Free section from Sparky Study Notes. The full Level 3 notes, 1,463 practice questions and the video lessons: sparkystudynotes.co.uk
Test yourself on it
The tests are in the members’ area. Get one wrong and it shows you why, and where to revise.
Get new notes and exam tips from Sparky
About one email a fortnight. Unsubscribe any time. Privacy noticeThat was one section. There are 583.
Sparky Study Notes is the whole Level 3 syllabus written up like this: the explanation, the worked example, and where it is in your book. With a video lesson for every part and a practice paper for every exam.
- 583sections of written notes
- 35video lessons
- 1,463practice questions
- 146diagrams, redrawn
- 18th Edition
- Building Regs
- PAT
- Fundamental Inspection & Testing
- Initial Verification
- Periodic Inspection & Testing